Enabling a client refresh, we excavated then added a concrete blinding before the steelwork and shuttering for both a cooler plinth and bund wall. Followed by adding concrete surge arrestor bases and a MEWP access concrete base before final mods and infill as required.
We used over 200m3 concrete in total, and this whole project was run extremely tight, due to delivery of the transformer from France, on a particular date.
Force Civils team worked extremely hard and came away with fantastic results, on time and on budget.