Delivering the installation of 96 precast parapet units across 120 metres of bridge deck was not simply a lifting exercise. It required disciplined planning, precise coordination and the experience of a highly skilled lifting team operating within a live infrastructure environment.
Each unit weighed approximately 9 tonnes and had to be lifted, rotated and placed under controlled conditions. On a programme where the road is scheduled to open in May, every movement on site needed to be carefully managed to maintain safety, protect programme and ensure quality installation.
Operations of this scale take place alongside other ongoing activities across the site. Access routes must remain clear, plant movements continue, and multiple teams operate within the same work area.
To maintain safe working conditions, the lifting operation was supported by detailed temporary works designs and a fully engineered lifting strategy. Crane positioning, exclusion zones and lift sequencing were carefully planned to ensure each movement could take place safely within a restricted footprint.
Clear communication across the site was essential. Every stage of the operation was briefed in advance, ensuring that all operatives understood the sequence of works and the safety measures in place.
Successful lifting operations begin long before the crane arrives on site. For this project, preparation focused on developing a structured plan that controlled each stage of the installation. This included:
– Detailed temporary works design
-A fully engineered lifting strategy
-450 tonne and 110 tonne cranes working in sequence
-Coordinated working within a restricted site area
-Precise delivery scheduling for the precast units
Each of these elements played a role in ensuring that the installation could progress smoothly without disruption to the wider programme.
Each precast parapet unit required careful handling during installation. The units were lifted into position, rotated where necessary and guided into place by an experienced lifting team.
Controlled lifting procedures ensured that every movement remained predictable and safe. Banksmen, lifting supervisors and crane operators worked closely together to maintain clear communication throughout the operation. Every lift was planned. Every risk assessed. Every step carried out with the attention to detail required on a safety critical infrastructure scheme.
The installation is progressing ahead of programme, demonstrating the value of strong planning at the earliest stages of the project. When complex works are properly structured from the outset, teams can operate with confidence, risks are controlled and productivity improves. Preparation removes uncertainty and allows skilled operatives to focus on delivering the work safely and efficiently. This is what disciplined planning achieves on large infrastructure schemes.
Infrastructure projects demand a level of planning and coordination that leaves no room for guesswork. Safety, quality and programme must be protected at every stage. By combining structured preparation, experienced operatives and clear leadership on site, complex lifting operations can be delivered safely and on schedule. That approach continues to guide the progress of this bridge parapet installation.
If you are planning a complex infrastructure scheme and need a contractor capable of delivering controlled, well coordinated installation works, speak to Force. We bring skilled teams, structured planning and disciplined delivery to every project.
📞 01909 509 475 | ✉ sales@forcecontracting.co.uk
High Security Fencing, Fencing, HVM Equipment, Bollards, Blockers, Barriers, Automated Gates & Integrated Systems, all associated civils, and more...
Residential Projects, Commercial Projects, Landscaping, Fencing & Railings, and more
Health and Safety, Environmental, Quality, Ethics, Compliance - consultancy support...